KEY TAKEAWAYS
- Prof. Marcelo Zas, MD, PhD, planned and built his own OR in Buenos Aires, Argentina—a dream that took 2 decades to realize.
- He chose state-of-the-art equipment to ensure it would contribute to surgical precision, safety, outcomes, and, ultimately, patient benefit.
- In October 2025, construction was complete, as was the required authorization to begin operations. The team formally inaugurated the Centro Oftalmológico Dr. Zas on December 2, 2025.
As is the case with most dream projects, building my own OR began long before the first blueprints were ever drawn.
After completing my residency at the University of Buenos Aires (UBA) and beginning my professional career alongside my mentors, I gradually developed my own experience as a vitreoretinal surgeon. Over the years, I had the opportunity to operate in many different ORs, both in Argentina and abroad. Each one taught me something about what worked well, what could be improved, and what a surgical team truly needs. Because of these varied experiences, an idea began to take shape: Someday, I would have my own OR, designed around my experiences as a surgeon and the needs of my patients and team.
For a decade, that idea remained a dream. In 2015, I decided to take concrete steps toward making it a reality and began searching for the right property—a search that took 3 years. From the beginning, I wanted a central location in Buenos Aires that would be accessible to patients and suitable for a comprehensive ophthalmic center. We decided to build from the ground up. This was an enormous challenge, but also a unique opportunity to design the facility without the limitations of an existing structure.
In this article, I share my experience designing and building an ophthalmic OR, as well as the pearls I learned along the way.
The OR was conceived, planned, constructed, and financed as an independent private project, without any institutional involvement from UBA. However, as of August 2026, the center is now formally affiliated with the UBA exclusively for academic and educational purposes, following a model adopted by many prestigious private medical centers in Argentina.
As a long-standing UBA faculty member, academic education, mentorship, and surgical training have always been essential components of my professional career. Since its inauguration, the OR has welcomed young ophthalmologists, residents, fellows, and visiting physicians from Argentina and abroad, fostering surgical observation and the training of future generations of ophthalmic surgeons.
DESIGNING FROM EXPERIENCE
A year after purchasing the property, the formal architectural, engineering, and interior design work began. Because of my experiences in different ORs, I had a clear vision of how I wanted the space to function; the challenge was translating that surgical vision into an architectural and technical reality. I partnered with professionals who had proven experience in health care facility design, particularly surgical environments, and a thorough understanding of regulatory requirements, infection control, and advanced medical technology.
During the planning and construction process, we paid particular attention to optimizing patient and surgical workflow, ensuring the efficient integration of reception, preoperative and postoperative areas, and the OR (Figure 1). Special emphasis was placed on infection control, sterilization circuits, HVAC systems, electrical safety, medical gases, surgical lighting, the integration of advanced ophthalmic technology, and compliance with regulatory requirements. It was important to prioritize functional design, patient safety, and future technological adaptability from the earliest planning stages.
Figure 1. Dr. Zas planned every aspect of the OR, from the architecture and engineering to the interior design and OR workflow.
THE EFFORT BEHIND THE DREAM
A project of this magnitude also requires long-term financial planning, and the project was funded entirely with personal resources, without external investors or business partners. In Argentina, bank financing can be relatively expensive, making self-financing through long-term financial planning and disciplined savings a more practical alternative. Physicians considering a similar investment must develop a realistic financial strategy well in advance, carefully assess the costs and risks, and prioritize financial independence whenever possible. Throughout this journey, my family has been fundamental. Their support and encouragement gave me the energy to take on the challenge and sustain it through to completion.
The goal was not simply to build a modern OR. We wanted a comprehensive surgical environment capable of supporting various ophthalmic specialties while remaining flexible enough to evolve with medicine and technology.
Construction began in 2020. From that point forward, the project moved from paper into reality, involving years of construction, decisions, modifications, and learning.
At the same time, we navigated the regulatory and licensing process required under Argentinian law. The dimensions and characteristics of the various spaces, infrastructure, and technical requirements all had to meet the standards necessary for approval.
The Ophthalmic Center was ultimately designed across two floors connected by an internal staircase, integrating consultation rooms, ophthalmic examination and diagnostic areas, and the OR to provide comprehensive care in a single location.
TECHNOLOGY AND THE HUMAN TEAM
Selecting the equipment was another central stage of the project. These decisions were based on many years of surgical experience and familiarity with different technologies used in surgical centers.
Technology is one of the fundamental pillars of a modern OR. Thus, we incorporated state-of-the-art equipment, not simply because it was sophisticated, but because it could contribute to surgical precision, safety, outcomes, and, ultimately, benefit the patient. I also chose equipment that integrates efficiently, offers consistent technical support, and allows for future upgrades.
Yet technology alone is never enough. The human team was another fundamental pillar. An OR is, above all, a team effort. Ophthalmologists and surgeons, scrub nurses, and circulating staff have different but complementary and indispensable roles. Coordination, communication, and trust are essential to performing every procedure safely and efficiently.
Ultimately, surgical excellence is the combination of experience, technology, and teamwork. Thus, I carefully selected the surgical staff through professional recommendations and personal interviews, prioritizing extensive previous experience, specialized training, and teamwork. Our surgical team includes an OR supervisor and two circulating staff members who assist during each procedure. All surgeries are performed by two surgeons working together, regardless of the ophthalmic subspecialty.
A PLACE TO CARE, OPERATE, AND TEACH
Education has been part of my professional life since I graduated from the Faculty of Medicine of UBA and has remained a constant throughout my career. Thus, I knew that the new OR must also be a place for teaching, and I designed it to welcome young physicians, residents, and physicians in training from Argentina and abroad to rotate through the center, observe procedures, and share in our surgical activities.
Figure 2. Incorporating 3D digital visualization in the OR allows visitors to observe procedures in real time.
An essential consideration was designing a spacious, comfortable, and technologically advanced OR that could also serve as an educational environment. The introduction of 3D digital visualization in the OR revolutionized my surgical teaching, allowing observers and surgical staff to see procedures in real time and gain a deeper understanding of surgical techniques and decision making (Figure 2).
An OR is not be only a place where surgery is performed; it’s also a place where knowledge is planted and cultivated. Sharing the experience, discussing surgical decisions and cases, and fostering learning for those beginning their careers is one way of giving future generations what I received from my own teachers and mentors.
Our goal is to contribute to the education of future vitreoretinal surgeons, as well as physicians pursuing other areas and subspecialties of ophthalmology. Physicians interested in rotating through our OR are welcome to contact my ophthalmology center directly by email or through any of our digital communication channels to request a clinical and surgical observership.
THE FIRST SURGERY AND BEYOND
In October 2025, construction was complete, and I had the authorization to begin operations. We officially inaugurated the Centro Oftalmológico Dr. Zas on December 2, 2025. The dream had come true.
Performing the first surgery (a 25-gauge vitrectomy for epiretinal membrane) was an indescribable moment. Before beginning, I thought back to my early years of training, my mentors, the many ORs in which I had worked, and the idea of my own OR emerging. I remembered the search for the location, planning, making all the decisions, watching the construction progress, and meeting all the challenges to reach that point.
In front of me was the completed OR, and I was surrounded by my team (Figure 3). I was entering a new home in which to pursue my professional passion, continue learning, perform surgery, and, above all, remain dedicated to my patients. Now a new chapter begins—putting this space, technology, team, and decades of learning to work helping patients and teaching those who will continue to shape the future of ophthalmology.
AI disclosure: ChatGPT (GPT-6 , OpenAI) was used to assist with language editing, grammar, clarity, and stylistic refinement. The original concept, personal experiences, clinical perspectives, and intellectual content were provided entirely by the author, who carefully reviewed, revised, and approved the final manuscript and assumes full responsibility for its content.